HIVE Digital has finalized the acquisition of Bitfarms’ partially completed 200-megawatt Bitcoin mining facility in Yguazú, Paraguay, for $56 million. The deal includes an upfront payment of $25 million due at closing in the first quarter of 2025, with the remaining $31 million to be paid in six equal monthly installments. According to an announcement HIVE made on January 28, the Yguazú facility will be developed in two stages. Phase 1, which is already 80% finished, is scheduled for completion by April 1, 2025. Phase 2, expected to be wrapped up by August 31, 2025. HIVE will assume $19 million in pre-existing PPA deposits that Bitfarms paid to Paraguayan utility ANDE.